Fukushima Experimental Offshore Floating Wind Farm Project Second Phase Update

TOKYO, June 22, 2015 - (JCN Newswire) - A consortium comprised of Marubeni (project integrator), the University of Tokyo (technical advisor), Mitsubishi, Mitsubishi Heavy Industries, Japan Marine United, Mitsui Engineering & Shipbuilding, Nippon Steel & Sumitomo Metal, Hitachi, Furukawa Electric, Shimizu, and Mizuho Information & Research, has been participating in an experimental offshore floating wind farm project sponsored by the Ministry of Economy, Trade and Industry since March 2012. Assembly works of the 7MW oil pressure drive-type wind turbine, which is the world's largest scale one, on the three-column semi-sub floater at Onahama port has been successfully completed and delivery of the floater to testing area is going to start shortly as part of the second term.

Fukushima Experimental Offshore Floating Wind Farm Project

1. Outline of construction works in the second term:
- Assembly and setting of 7MW oil pressure drive-type and 5MW downwind-type floating
wind turbines, delivery of the facilities to the testing area, and connection to the undersea cable.
- Operation & Maintenance of the facilities
- Data acquisition and analysis.

2. Work progress to date:
<7MW oil pressure drive-type floating wind turbine>
- Preceding works i.e. installation of chains, anchors and undersea cables at the testing area has been successfully completed.
- Delivery of the three-column semi-sub floater from Nagasaki to Onahama port has been successfully completed.
- Installation of 7MW oil pressure drive-type floating wind turbine on the floater at Onahama port has been successfully completed.

<5MW downwind-type floating wind turbine>
- Procurement of chains and anchors, and production of high-voltage riser cable have been successfully completed.
- Parts procurement and construction of 5MW downwind-type floating wind turbine is in progress.

3. Next Step
The following activities need to be completed to start operation of the power facilities:
- Schedule will be changed depending on the meteorological and sea conditions

Contact:
Hideo Ikuno
h.ikuno@daiya-pr.co.jp 
+81-3-6716-5277



Topic: Press release summary
Source: Mitsubishi Heavy Industries, Ltd.

Sectors: Energy, Alternatives, Alternative Energy
https://www.acnnewswire.com
From the Asia Corporate News Network


Copyright © 2024 ACN Newswire. All rights reserved. A division of Asia Corporate News Network.

 
Mitsubishi Heavy Industries, Ltd. Links

http://www.mhi.com

https://www.mhi.com/rss/

https://www.facebook.com/mhi.ltd/

https://twitter.com/MHI_Group

https://www.youtube.com/user/DiscoverMHI

https://www.linkedin.com/company/mitsubishi-heavy-industries/

Mitsubishi Heavy Industries, Ltd. Related News
Friday, 20 December 2024, 17:24 JST
Contract Renewed on Operation and Maintenance (O&M) Services for APM System at Washington Dulles International Airport
2024年12月20日 10時30分 JST
三菱重工グループCrystal Mover Services、米国ワシントン・ダレス国際空港のAPMシステム運行・保守(O&M)契約を更新
2024年12月19日 13時30分 JST
三菱重工、防衛省向け3,900トン型護衛艦「ながら」の命名・進水式を長崎で実施
Thursday, 19 December 2024, 13:49 JST
MI LNG Company to Change Corporate Name to MILES
2024年12月19日 10時36分 JST
三菱重工と今治造船の合弁会社であるMI LNGを「MILES」へ社名変更
More news >>
Copyright © 2024 ACN Newswire - Asia Corporate News Network
Home | About us | Services | Partners | Events | Login | Contact us | Cookies Policy | Privacy Policy | Disclaimer | Terms of Use | RSS
US: +1 214 890 4418 | China: +86 181 2376 3721 | Hong Kong: +852 8192 4922 | Singapore: +65 6549 7068 | Tokyo: +81 3 6859 8575