MHPS Beats Original Estimates for Upgrading the H-100 Gas Turbine by 24 Days
- Retrofitting of the No. 4 Unit of the No. 2 Group Generator at the TEPCO Group's Futtsu Power Station -

- Achieved by enhancing the transport efficiency for heavy items, and improving the procedures for trial operations
- Quicker upgrade period will help increase partnership opportunities, and enhance the operating efficiency of existing power facilities

YOKOHAMA, Japan, Aug 6, 2018 - (JCN Newswire) - Mitsubishi Hitachi Power Systems, Ltd. (MHPS) beat original estimates by 24 days in upgrading the H-100 gas turbine. The expedited process was implemented during the retrofitting project for the No. 2 group power generating unit at the Futtsu Power Station, located in the bay area of Futtsu, Chiba Prefecture, and operated by TEPCO Fuel & Power, Inc. (TEPCO FP), which handles the thermal power generation and fuel business for the TEPCO Group.

Renewal Work for Gas Turbine (Source:TEPCO Fuel & Power, Inc)

In replacing a high-efficiency H-100 gas turbine with a rated output of 120MW class, MHPS focused on enhancing the transport efficiency of heavy items and refining overall procedures. While the installation period is typically 180 days, the project was completed 24 days earlier, in just 156 days. MHPS will leverage the success of this new process to increase sales of the H-100 series and enhance solutions to improve the operations rate of existing power generating facilities.

The No. 2 group unit is a gas turbine combined cycle (GTCC) generating facility, comprising of seven units with a rated output of 1,120MW (160MW x 7 units). The retrofitting of the group unit began in February 2016, with successive renewals of gas and steam turbines. The 24 day reduction in lead time was initiated to replace the No. 4 unit and completes the renewal work for five of the seven units. The renovation has significantly increased the power generating efficiency of the No. 4 unit, from 47.2% to 54.3%, and is expected to lower fuel costs by around JPY1.3 billion annually, and reduce CO2 emissions by around 60,000 tonnes.

Since starting the renewal of the initial unit, MHPS along with the cooperation of TEPCO FP, has employed various techniques to shorten lead times. Particularly successful were efforts to connect (modify) two overhead cranes in order to wholly suspend heavy items and revise testing requirements during test operations. Proficiency with new endeavors aided these efforts, and produced this highly effective result. It has been two and a half years since the renovation of the initial unit, which has operated stably for 12,000 hours, with over 250 start-ups and stops. Considering this high degree of stability and reliability, MHPS will extend the period between regular maintenance to further lower maintenance costs and complete remaining renewal work for two units in a short period.

The H-100 is a heavy-duty(Note) two-shaft gas turbine in the 120MW class, with world-leading capacity in a two-shaft system, that delivers flexible, quick-response operation. Users also appreciate the H-100's fast start-up time and moderate space requirements. The addition of shorter renovation time is expected to further enhance its market competitiveness.

MHPS is in a position of strength due to its ability to provide total solutions in power generation. The company offers a full range of products for thermal power plants, from high-efficiency, large-capacity generation systems, to energy-saving systems utilizing small and medium-size gas turbines. Going forward, while responding accurately to the diverse needs of the market, MHPS will continue to contribute to a stable power supply, promote low-carbon energy, and enhance conservation of the global environment.

Gas turbines designed to maintain a consistent output with continual operation over long periods, with simple and less frequent maintenance.

http://www.acnnewswire.com/topimg/Low_FuttsuPowerStation.jpg
Futtsu Power Station (Source:TEPCO Fuel & Power, Inc)

http://www.acnnewswire.com/topimg/Low_RenewalWorkGasTurbine.jpg
Renewal Work for Gas Turbine (Source:TEPCO Fuel & Power, Inc)

Contact:
Joseph Hood, PR Manager
Mitsubishi Heavy Industries, Ltd.
Email: mhi-pr@mhi.co.jp
Tel: +81-3-6716-2168
Fax: +81-3-6716-5860


Topic: Press release summary
Source: Mitsubishi Heavy Industries, Ltd.

Sectors: Energy, Alternatives
https://www.acnnewswire.com
From the Asia Corporate News Network


Copyright © 2026 ACN Newswire. All rights reserved. A division of Asia Corporate News Network.

 
Mitsubishi Heavy Industries, Ltd. Links

http://www.mhi.com

https://www.mhi.com/rss/

https://www.facebook.com/mhi.ltd/

https://twitter.com/MHI_Group

https://www.youtube.com/user/DiscoverMHI

https://www.linkedin.com/company/mitsubishi-heavy-industries/

Mitsubishi Heavy Industries, Ltd. Related News
Wednesday, 4 February 2026, 17:13 JST
Mitsubishi Heavy Industries Announces Large Order Intake, Revenue, and Profit Growth in First Three Quarters, Raises Full-Year Guidance
Wednesday, 28 January 2026, 18:08 JST
MHI Thermal Systems Receives "Minister of Economy, Trade and Industry Award" and MHI's Aerospace Parts Factory Receives "Agency for Natural Resources and Energy Commissioner's Award" at 2025 Energy Conservation Grand Prize Awards
2026年1月28日 17時00分 JST
2025年度「省エネ大賞」で三菱重工サーマルシステムズが「経済産業大臣賞」、三菱重工の航空宇宙部品工場が「資源エネルギー庁長官賞」を受賞
2026年1月26日 14時30分 JST
三井物産が設立した宇宙ベンチャー「日本低軌道社中」に対し三菱重工、三菱電機が出資
Monday, 26 January 2026, 13:24 JST
Mitsubishi Heavy Industries and Mitsubishi Electric Invest in Japan LEO Shachu, a Space Venture Established by Mitsui & Co.
More news >>
Copyright © 2026 ACN Newswire - Asia Corporate News Network
Home | About us | Services | Partners | Events | Login | Contact us | Cookies Policy | Privacy Policy | Disclaimer | Terms of Use | RSS
US: +1 214 890 4418 | China: +86 181 2376 3721 | Hong Kong: +852 8192 4922 | Singapore: +65 6549 7068 | Tokyo: +81 3 6859 8575