|
|
|
|
-- Fourth M701JAC Unit Begins Operation at Power Plant Jointly Owned by IPP Gulf Group and Mitsui & Co., Ltd. --
- The completion of the GTCC power plant in Chonburi Province will contribute to the stable supply of clean power as the country aims to achieve net-zero emissions by 2050. - A ceremony was held to commemorate the project finishing on schedule despite challenges brought about by the COVID-19 pandemic. |
TOKYO, Oct 6, 2022 - (JCN Newswire) - Mitsubishi Power, a power solutions brand of Mitsubishi Heavy Industries, Ltd. (MHI), has commenced operation of the fourth and final M701JAC unit at an ultra-large-scale natural gas-fired power plant in Chonburi Province, Thailand, on 1 October 2022. The plant is owned by a joint venture of Gulf Energy Development PCL, one of the largest independent power producers in Thailand, and Mitsui & Co., Ltd.
| The GTCC Power Plant in Chonburi |
| Takashi Tozawa (Deputy Head of Energy Transition & Power Headquarters, Senior General Manager, GTCC Business Division/MHI) (2nd from left), Junta Sasaji (Managing Director/Mit-Power Capitals (Thailand) Limited) (3rd from left) and Natcharee Pongrattanadej (Deputy COO/Gulf Energy Development PCL) (3rd from right) together with representatives from the Electricity Generating Authority of Thailand and Sino-Thai Engineering and Construction PCL at the completion ceremony of the GTCC Power Plant in C |
This milestone, which was commemorated with a ceremony in the Chonburi facility, signals the completion of one of two 2,650 MW gas turbine combined cycle (GTCC) thermal power generation systems in Thailand whose full-turnkey orders for construction were secured by Mitsubishi Power in 2018. Construction of the second power plant project is currently underway in Rayong Province.
The Chonburi power plant is located approximately 130 km southeast of Bangkok, and is operated by the joint venture Gulf SRC Company Limited*. The first unit has already been in commercial operation for 1.5 years, the second unit for one year, and the third unit for six months - and all three boast high operating rates. In September 2022, the M701JAC gas turbine of the first unit achieved 8,000 actual operating hours (AOH), establishing an industry benchmark of reliability.
The GTCC power generation equipment in this project consists of four power trains per power plant, each made up of four subsystems: a M701JAC gas turbine, steam turbine, heat recovery steam generator, and generator. Although constraints arose due to the COVID-19 pandemic in areas such as equipment transport and travel by local lead engineers, construction of the Chonburi power plant progressed according to the original plan thanks to the ingenuity and hard work of the people involved, including activation of remote installation support and use of alternative construction methods.
Gulf Energy Development PCL highly praised Mitsubishi Power's construction and engineering capabilities: "For more than 10 years, Gulf Energy and Mitsubishi Power have built a solid relationship of trust, and the completion of this GTCC power exemplifies this. Mitsubishi Power carried out this project as a unified team, and we are grateful for Mitsubishi Power's commitment and resilience to have all four power trains commence operations in line with agreed delivery dates, even amid the difficulties of the COVID-19 pandemic."
Mr. Takashi Tozawa, Deputy Head of Energy Transition & Power Headquarters, Senior General Manager, GTCC Business Division of MHI, was equally proud of this unparalleled achievement: "Thanks to the cooperation of everyone involved, we have achieved commercial operation of all four power trains without incident, according to the original contract schedule. We are proud to say this is the only project in Thailand which began operation on time, despite the COVID-19 pandemic. I am certain that our solid relationship of over 10 years with customers in Thailand will lead to similar success of the project currently under construction in Rayong Province."
Together with Mr. Takashi Tozawa, Ms. Natcharee Pongrattanadej, Deputy COO of Gulf Energy Development PCL, and Mr. Junta Sasaji, Managing Director of Mit-Power Capitals (Thailand) Limited, a Mitsui subsidiary company, also graced the completion ceremony.
As it focuses on finishing the power plant in Rayong Province, Mitsubishi Power will continue to step up efforts to promote widespread adoption of state-of-the-art JAC-type gas turbines, thus helping ensure the stability of electric power essential for economic development in various regions of the world, while reducing the environmental impact of power generation.
*The power plant in Rayong Province is operated by Gulf PD Company Limited.
About MHI Group
Mitsubishi Heavy Industries (MHI) Group is one of the world's leading industrial groups, spanning energy, smart infrastructure, industrial machinery, aerospace and defense. MHI Group combines cutting-edge technology with deep experience to deliver innovative, integrated solutions that help to realize a carbon neutral world, improve the quality of life and ensure a safer world. For more information, please visit www.mhi.com or follow our insights and stories on spectra.mhi.com.
Topic: Press release summary
Source: Mitsubishi Heavy Industries, Ltd.
Sectors: Energy, Alternatives
https://www.acnnewswire.com
From the Asia Corporate News Network
Copyright © 2024 ACN Newswire. All rights reserved. A division of Asia Corporate News Network.
|
|
|
|
|
|
|